Building a house and land package is one of the most structured ways to get into your first home. But that does not mean it is simple. The step by step building house and land package process involves ten distinct phases, each with its own timeline and decisions. Understanding what happens at every stage removes the uncertainty and puts you in control.
This guide walks through the complete house and land package process in chronological order. Every step includes what happens, how long it takes, and what you need to do. These timelines are based on Senka’s experience building across Melbourne’s growth corridors.
Timeline summary
Before we get into the detail, here is the big picture.
Total process from pre-approval to handover: approximately 12 to 18 months.
Pre-construction phase (Steps 1 to 6): 3 to 6 months. This covers finance, land selection, design selection, contracts, colour consultation, building permit, and pre-site works.
Construction phase (Steps 7 to 9): 7 to 12 months. This covers the physical build from slab to practical completion.
Post-handover (Step 10): 1 to 2 weeks to settle, move in, and begin the warranty period.
The pre-construction phase is where most delays occur. Land registration, finance approval, and building permit timelines are largely outside your builder’s control. Choosing a registered block with an approved builder shortens this window significantly.
Step 1: Get your finance pre-approved
Everything starts with your borrowing capacity. Before you look at land, before you explore home designs, you need to know what you can spend. A finance pre-approval gives you a confirmed borrowing limit from a lender, valid for 90 days.
What happens. You meet with a mortgage broker or lender. They assess your income, debts, expenses, and savings. If eligible, they issue a conditional pre-approval letter confirming how much they are willing to lend. For a house and land package, you will need a construction loan, not a standard home loan. Funds are released in stages as the build progresses, not as a lump sum at settlement. We cover this in detail in our construction loans guide.
How long it takes. 1 to 3 weeks from application to pre-approval. Complex applications involving self-employment or multiple income sources may take longer.
What you need to do. Gather your last two payslips, three months of bank statements, proof of identity, your most recent tax return (if self-employed), and details of any existing debts. Ask your broker specifically about construction loan products and make sure the pre-approval covers the total package price, not just the land component.
Senka tip. Do not skip this step. We see buyers fall in love with a block and a design before knowing their budget, only to discover the numbers do not work. Pre-approval protects you from that scenario.
Step 2: Choose your location and block
With your budget confirmed, you can start looking at land. In Melbourne, most house and land packages are built in growth corridor estates in suburbs like Tarneit, Truganina, Wyndham Vale, Clyde North, Craigieburn, and Mickleham. Each suburb has a different profile in terms of land price, lot size, infrastructure, school zoning, and commute time.
What happens. You research estates, visit display villages, and shortlist blocks that suit your budget and lifestyle. Key decisions include lot width (which determines what home designs will fit), orientation (which affects natural light and energy efficiency), and estate stage (which affects when the land will be titled and registered).
A common question is whether you choose the land or the house first. Land comes first, because the lot dimensions and orientation dictate which designs are suitable. A 12.5 metre wide lot supports a different range of floor plans than a 16 metre wide lot.
How long it takes. 1 to 4 weeks of active searching. If you are purchasing in a future release, land registration can take 6 to 18 months. Titled land can settle within 30 to 90 days.
What you need to do. Visit estates in person. Check the plan of subdivision for easements, setbacks, and encumbrances. Confirm whether the land is titled or untitled and ask the developer for their estimated registration date.
Senka tip. We work with land agents across every major growth corridor and can match you to blocks that suit specific designs in our range. This avoids the mistake of buying a block that does not work with the home you want.

Step 3: Select your home design
Once you have identified your block, you select a home design that fits the lot dimensions, meets the estate’s design guidelines, and suits your household.
What happens. You review the builder’s range of designs, filter by lot width, and shortlist homes that match your bedroom count, living areas, and budget. Many buyers begin online, then visit a display home to see the spaces in person. This is also where you discuss modifications. Extending the alfresco, adding a theatre room, or changing the garage configuration all need to be quoted and confirmed before the contract stage.
How long it takes. 1 to 3 weeks for most buyers. Longer if you are comparing multiple builders or requesting custom modifications.
What you need to do. Bring your lot plan and any estate design guidelines to the appointment. Ask for a fixed price quote that includes all standard inclusions, site costs, and any modifications. Do not compare builders on base price alone. The difference is almost always in what is included, not the headline number.
Senka tip. Every Senka quote includes our full inclusions schedule. Concrete driveway, landscaping to front and rear, 900mm appliances, stone benchtops, ducted heating, and items that other builders charge as extras. The cheapest base price often becomes the most expensive build once you add in what was left out.
Step 4: Sign the contracts (land and build)
A house and land package involves two separate contracts: one with the land developer and one with the builder. They are linked but legally independent.
What happens. You sign the contract of sale for the land and the domestic building contract for construction. In Victoria, the building contract must be a fixed price contract under the Domestic Building Contracts Act 1995. The total price is locked in before construction begins, with limited exceptions for allowances and prime cost items.
Both contracts go to your lender for formal approval. The lender reviews the building contract, confirms the builder’s registration, and issues a formal loan approval replacing your conditional pre-approval.
How long it takes. 1 to 3 weeks for contract preparation and signing. Another 2 to 4 weeks for formal finance approval.
What you need to do. Read every page of both contracts. Pay attention to the inclusions schedule, provisional sums, start and completion dates, and the cooling off period. In Victoria, you have five business days to cool off from a domestic building contract without penalty. Use that time. If something is not in the contract, it is not in the build.
Your deposit on the building contract is typically 5 percent, payable at signing. The land deposit is negotiated with the developer, usually $1,000 to $5,000 on exchange.
Senka tip. We walk every client through the contract line by line. Understanding what you are agreeing to protects you and protects us. Transparency at contract stage prevents disputes at construction stage.
Step 5: Complete your selections and colour consultation
This is where your home becomes personal. Before construction begins, you need to finalise every material selection for your build.
What happens. You attend a colour consultation, either at a display home, a selections studio, or both. This appointment covers external and internal selections including roof tiles, facade materials, brick or render colours, window frames, flooring, cabinetry, tapware, tiles, benchtops, and paint colours. You also finalise any electrical upgrades (extra power points, data points, pendant lights) and confirm your kitchen and bathroom layouts.
Selections need to be completed before the building permit application, because the working drawings require final specifications. Delays in selections directly delay the permit, which delays construction.
How long it takes. 1 to 3 weeks. The consultation itself takes 2 to 4 hours.
What you need to do. Come prepared. Browse supplier websites in advance. Bring photos of interiors you like. Make decisions in the appointment where possible, because indecision here becomes a delay on site. Bring your contract to confirm what is included in the base price and what will be quoted as an upgrade.
Senka tip. Our colour consultation process is structured to make decisions easier, not harder. We guide you through a curated palette that works with your facade and floor plan, rather than handing you a catalogue of 400 tile options and wishing you luck.

Step 6: Building permit and pre-site
Before a single trench is dug, your build needs a building permit. This is the regulatory gateway between planning and construction.
What happens. Your builder prepares the working drawings based on your signed contract and completed selections. These are submitted to a registered building surveyor along with engineering plans, energy rating (7 star minimum under the National Construction Code from 1 May 2024), and a BAL assessment if applicable. The surveyor reviews the documentation and issues a building permit.
Simultaneously, if your land has settled, your builder coordinates pre-site works including the site cut, temporary fencing, site shed, and connection to services. Council and developer requirements for stormwater, crossover, and street tree protection vary by estate.
How long it takes. 2 to 6 weeks for the building permit, depending on the complexity of the design and the surveyor’s workload. Pre-site works take 1 to 2 weeks once the permit is issued.
What you need to do. At this stage, your main role is to stay responsive. If the surveyor or builder needs clarification on selections, boundary setbacks, or engineer queries, delays in your response delay the permit. Confirm your contact details are up to date and respond to queries within 24 to 48 hours.
Senka tip. We lodge the building permit application as soon as selections are finalised. Our pre-site coordinator manages the entire process from survey through to slab preparation, so you have a single point of contact during this phase.
Step 7: Construction begins
This is where your investment becomes physical. Construction follows a prescribed sequence of stages, each with defined milestones and progress payments.
What happens. The build progresses through the stages of building a home as defined in your contract and regulated under the Domestic Building Contracts Act 1995. The standard stages are as follows.
Base stage (slab). Excavation, footings, plumbing rough-in, and concrete slab pour. This is the foundation of your home. Once the slab is poured and cured, you will see the outline of every room on the ground.
Frame stage. Structural timber or steel framing goes up, roof trusses are installed, and the roof is sheeted. At this point, the home takes shape and you can walk through the rooms.
Lock up stage. External cladding, brickwork, windows, external doors, and roof covering are completed. The home is weather sealed. This is the largest progress payment.
Each stage triggers a progress claim, submitted to your lender for drawdown. You only pay interest on the amount drawn so far. For a full breakdown, see our construction loans guide and our stages of building guide.
How long it takes. Base to lock up typically takes 10 to 16 weeks, depending on weather, trade availability, and the size of the home.
What you need to do. Approve progress claims promptly. Each claim includes photos and a description of completed work. Review them, compare against your contract stages, and forward to your lender. Delays in claim approval can slow the build.
Step 8: Progress inspections and updates
Construction does not happen in a black box. You should receive regular updates and have the opportunity to visit the site at defined stages.
What happens. After lock up, the build enters the fixing and fit-off stages.
Fixing stage. Internal wall linings (plasterboard), architraves, skirting boards, internal doors, cabinetry, bathroom waterproofing and tiling, kitchen installation, and built-in robes are completed.
Fit-off stage. Tapware, toilets, basins, electrical fixtures, smoke alarms, mirrors, shower screens, and final paint are completed. External works including the driveway, paths, and landscaping are also finished during this period.
Your builder should provide regular communication through photos, emails, or a client portal. At Senka, we provide updates at each stage milestone and invite clients to attend frame stage and pre-handover inspections. Frame stage is your opportunity to walk through and confirm that everything matches the plans before the walls go up.
How long it takes. Fixing through to fit-off takes 8 to 14 weeks. The H&L package timeline for the full construction phase is typically 7 to 12 months depending on the size and complexity of the home.
What you need to do. Attend inspections when invited. Take photos. Ask questions. If something does not look right, raise it immediately. It is far easier to resolve a concern during construction than after handover. Keep a record of all communication with your builder.
Senka tip. We encourage site visits at frame stage and pre-handover. An informed client is a confident client. We would rather answer 20 questions during the build than one complaint after you move in.

Step 9: Practical completion and handover
This is the finish line. Your home is complete, inspected, and ready for you to take possession.
What happens. Once all construction work is finished, your builder notifies you that the home has reached practical completion. An independent building surveyor issues an occupancy permit confirming that the home complies with the building permit and the National Construction Code.
You then attend a pre-handover inspection (PCI). This is your opportunity to walk through the completed home with the site supervisor and identify any items that need rectification. Common items include paint touch-ups, adjustments to doors or cabinetry, silicon sealing, and cleaning.
Defects identified at PCI are documented and rectified before or shortly after handover. The final progress payment (completion stage, typically 10 percent) is payable once the occupancy permit is issued and agreed defects are addressed.
How long it takes. 1 to 3 weeks from practical completion notification to key handover.
What you need to do. Attend the PCI and document everything. Take photos. Be thorough but reasonable. Hairline shrinkage cracks in plaster are normal. A door that does not latch properly is a defect. Know the difference.
Senka tip. We conduct our own internal quality inspection before inviting you to the PCI. Our aim is that when you walk through, the home is genuinely finished. We do not use the PCI as a to-do list for work that should have been completed.
Step 10: Move in and settle
You have the keys. The build is done. But the process has one more phase.
What happens. You move in, set up your utilities, and begin living in your new home. Your builder’s obligations do not end at handover. Under Victorian legislation, statutory warranties protect you for six years for structural defects and two years for non-structural defects from the date of the occupancy permit.
Your conveyancer coordinates the final settlement with your lender. Once settled, the property transfers into your name and your mortgage begins standard principal and interest repayments.
How long it takes. Settlement typically occurs within 14 days of handover.
What you need to do. Arrange connections for electricity, gas, water, internet, and council services before your move-in date. Keep a copy of your building contract, plans, occupancy permit, and maintenance guides. If you notice any defects in the first few months, document them and notify your builder in writing.
Senka tip. We provide a maintenance guide at handover on every house and land package that covers seasonal care for your new home. Timber shrinkage in the first 12 months is normal. Cracks in cornice joins and nail pops in plasterboard are standard settling behaviour, not defects. We return at the 90 day mark for a maintenance visit to address these items as part of our standard process.
Frequently asked questions
How long does a house and land package take from start to finish?
Approximately 12 to 18 months from finance pre-approval to handover. The pre-construction phase takes 3 to 6 months and the construction phase takes 7 to 12 months. Titled land and straightforward designs sit at the shorter end. Untitled land and larger homes push toward the longer end.
What happens after you sign a house and land contract?
Both contracts go to your lender for formal finance approval. Once approved, you complete your colour consultation, your builder prepares working drawings, and the building permit is lodged. Once the permit is issued and the land has settled, construction begins. The stages of building H&L follow a prescribed sequence from slab through to handover, with progress payments at each milestone.
Do you choose the land or the house first?
Land first. The lot dimensions, orientation, setbacks, and estate design guidelines determine which home designs will fit. A 12.5 metre lot suits a different range of homes than a 16 metre lot. Starting with the land ensures you select a design that works on the block and meets your budget.
When do you start paying for a house and land package?
Your first payment is the deposit on the land contract, typically $1,000 to $5,000 on exchange. Your building deposit (5 percent of the contract price) is paid when you sign the building contract. After that, you pay interest only on progressive drawdowns during construction. Full principal and interest repayments begin once the build is complete and the final drawdown is processed. For a detailed breakdown of how to buy a house and land package and manage the payment schedule, see our construction loans guide.