Demolishing a house in Melbourne is the first physical step in a knockdown rebuild, and it is the stage where the most avoidable mistakes happen. Permits get missed, asbestos gets discovered late, services are disconnected in the wrong order, and the whole project timeline blows out before a single footing is poured. The demolition itself is straightforward. The preparation and compliance around it is where the real work sits.
This guide covers every step of the demolition process in practical detail, from council permits through to site preparation for the new build. If you are still in the planning phase of your knockdown rebuild, start with our knockdown rebuild Melbourne guide for the full picture before focusing on demolition specifics.
Council Permits for Demolition
Every house demolition in Melbourne requires a building permit, and in many cases additional council consents or a planning permit. The building permit is mandatory and is issued by a registered building surveyor, either a council surveyor or a private building surveyor. This permit confirms that the demolition will be carried out safely and in accordance with the Building Act 1993. In addition, where the proposed demolition exceeds 50 per cent of an existing building or involves any part of the facade, council report and consent is required under Section 29A of the Building Act 1993. For a full knockdown rebuild this is generally triggered.
A planning permit may also be required depending on heritage status, overlay controls, and your local council’s rules. Properties in heritage overlay zones, neighbourhood character areas, or vegetation protection zones almost always require a planning permit, which can take 8 to 12 weeks to process.
Section 29A application fees typically range from $500 to $1,500 depending on the municipality. The building surveyor’s fee for the demolition building permit varies by surveyor. The planning permit application fee, if required, is set under state regulations and currently sits at approximately $1,350 for a standard residential application. Your demolition contractor or builder should confirm which permits and consents are needed, but it is your responsibility as the property owner to ensure they are in place before work commences.
At Senka, we coordinate the permit process as part of the overall knockdown rebuild project. Our building surveyor assesses the site, identifies any overlay requirements, and ensures both the demolition and new build permits are processed together to avoid delays between stages.
Asbestos Inspection and Removal
Any home built before 1990 in Australia has a reasonable probability of containing asbestos materials. Homes built before 1970 have a very high probability. Under Victorian law, a hazardous materials assessment must be carried out before any demolition work begins, and if asbestos is identified, it must be removed by a licensed asbestos removalist before the demolition contractor can proceed.
Common locations include eave linings, internal wall sheeting (particularly wet areas), floor tiles, fencing, roof sheeting on fibro homes, and pipe insulation. A qualified occupational hygienist inspects the property, takes samples, and provides a report identifying all asbestos containing materials. This inspection costs $300 to $800.
Removal costs depend on quantity and type. Non-friable asbestos (bonded sheeting) is less expensive to remove than friable asbestos (loose insulation). For a typical three bedroom home with asbestos eaves and wet area linings, removal costs sit between $5,000 and $15,000. Extensive asbestos throughout the structure can exceed $20,000. These costs are separate from demolition and need to be budgeted as a standalone line item.
Licensed removalists must follow strict WorkSafe Victoria protocols including air monitoring, containment barriers, and approved disposal. A clearance certificate is provided once complete, and must be available before demolition commences.
Disconnecting Services (Gas, Water, Electricity)
Before demolition can begin, all utilities connected to the property must be disconnected and made safe. This includes electricity, gas, water, sewer, and telecommunications. Each service has its own disconnection process and timeline, and failing to coordinate them properly is one of the most common causes of demolition delays.
Electricity disconnection is handled by your electricity distributor (not your retailer). You need to submit an abolishment request, which permanently removes the connection to the property. This process takes 10 to 20 business days and costs between $200 and $600. Temporary power for the new build will be arranged separately once construction begins.
Gas disconnection follows a similar process through your gas distributor. The gas meter is removed and the service is cut at the main, taking approximately 10 to 15 business days. Water and sewer disconnection requests go to your local water authority. A plumber may need to cap the water and sewer connections at the property boundary.
Telecommunications services including NBN and any legacy copper lines need to be disconnected through the respective providers. If your property has an Opticomm fibre connection, this should be documented and communicated to the builder so it can be reconnected during the new build. At Senka, Opticomm fibre is a standard inclusion in every home we build, so we ensure the connection is preserved and integrated into the new property from the outset.

Choosing a Demolition Contractor
Not all demolition contractors are the same, and the cheapest quote is rarely the best value. A reputable demolition contractor in Melbourne should hold a current demolition licence from the Victorian Building Authority, carry adequate public liability and workers compensation insurance, and have experience with residential demolitions in your local council area.
Ask for at least three quotes, and make sure each quote covers the same scope: demolition of the structure, removal of all debris, site levelling, and any necessary tree removal or retention measures. Some contractors quote for the demolition only and then charge separately for site clean-up, skip bins, and stormwater pit removal, which inflates the final cost well beyond the initial quote.
Check that the contractor will obtain the building permit for demolition (if this is not being handled by your builder or building surveyor), arrange the asbestos clearance certificate, and manage all waste disposal to licensed facilities. They should also provide a demolition plan that outlines the sequence of work, traffic management if the site is on a busy road, and any temporary fencing requirements.
At Senka, we have an established network of demolition contractors we work with regularly across Melbourne. We manage the quoting, appointment, and coordination of the demolition contractor as part of our end to end KDR process. This means the client does not need to independently source and manage a demolition company while simultaneously planning their new build.
What Demolition Costs in Melbourne
The cost to demolish a house in Melbourne varies based on the size of the structure, the presence of asbestos, the accessibility of the site, and any council specific requirements such as tree protection or neighbour notification. For a standard single storey house on an accessible suburban block, full demolition including all permits, asbestos removal, service disconnections, and site clean-up typically costs between $25,000 and $45,000.
Double storey homes cost more due to additional structural complexity and material volume. Expect to pay between $35,000 and $60,000 for a two storey demolition. Factors that increase costs beyond the base price include extensive asbestos, difficult site access requiring smaller equipment, tree protection requirements, retaining walls, and shared walls with adjoining properties that require engineering assessment.
For a detailed breakdown of how demolition costs fit into the total project budget, see our guide on knockdown rebuild costs in Melbourne. The demolition phase typically represents 5% to 10% of the total KDR project cost.
How Long Demolition Takes
The physical demolition of a standard single storey house takes 3 to 5 days. A double storey home takes 5 to 8 days. These timeframes assume the site is fully prepared: all services are disconnected, asbestos has been removed, permits are in place, and the demolition contractor has clear access to the site.
The total timeline from decision to site clearance is significantly longer. Allow 6 to 10 weeks for the full process: asbestos inspection (1 to 2 weeks), asbestos removal if required (1 to 2 weeks), service disconnections (2 to 4 weeks, running concurrently), building permit (1 to 2 weeks with a private surveyor), and demolition works plus site clean-up (1 to 2 weeks).
Weather can affect the timeline, particularly heavy rain which makes it unsafe to operate heavy machinery on soft ground. In Melbourne’s wetter months between May and September, allow an additional buffer of one to two weeks.
Preparing the Site for the New Build
Once the existing house is demolished and all debris is removed, the site needs to be prepared for construction. This is not simply a matter of clearing the rubble. The site must be assessed for soil conditions, any remaining underground structures such as old footings, septic tanks, or cisterns must be removed, and the ground must be graded to the levels specified in the engineering plans for the new home.
A soil test, also known as a geotechnical investigation, is conducted at this stage if one has not already been completed during the design phase. The soil test determines the classification of the site (ranging from A for stable sand/rock through to P for problem sites requiring engineered foundations) and directly influences the footing design and cost. In Melbourne, reactive clay soils are common, and many established suburbs sit on Class M (moderately reactive) to Class H (highly reactive) soil, which requires deeper footings and more robust slab design.
Stormwater and drainage connections are also assessed during site preparation. The location of existing stormwater pits, the connection point to the council drain, and any easements or overland flow paths must be mapped and accounted for in the new design. At Senka, our site assessment covers all of these elements before construction begins, ensuring there are no surprises once the building stages commence.

Frequently Asked Questions
Do I need a permit to demolish a house in Melbourne?
Yes. A building permit is required for all residential demolitions in Victoria, issued by a registered building surveyor. Where the demolition exceeds 50 per cent of the existing building, or involves any part of the facade, council report and consent under Section 29A of the Building Act 1993 is also required. If your property is in a heritage overlay, neighbourhood character overlay, or vegetation protection zone, you will also need a planning permit from your local council. Section 29A fees typically range from $500 to $1,500. The planning permit application fee for a standard residential application is approximately $1,350. Always confirm the permit requirements with your building surveyor or builder before engaging a demolition contractor.
How much does it cost to demolish a house in Victoria?
For a standard single storey home in Melbourne, full demolition costs between $25,000 and $45,000 including permits, asbestos removal, service disconnections, debris removal, and site clean-up. Double storey homes cost between $35,000 and $60,000. The final cost depends on the size of the home, the quantity of asbestos materials, site accessibility, and any council specific requirements. These costs should be factored into your overall knockdown rebuild budget from the planning stage.
How do I check for asbestos before demolition?
Engage a licensed occupational hygienist or hazardous materials assessor to inspect the property and take samples of any suspect materials. This inspection costs between $300 and $800 and produces a report identifying all asbestos containing materials, their location, type, and condition. Under Victorian law, this assessment is mandatory before any demolition work begins on homes that may contain asbestos. Your demolition contractor or builder can recommend a qualified assessor, or you can find one through the Australian Institute of Occupational Hygienists directory.
How long does house demolition take?
The physical demolition takes 3 to 5 days for a single storey home and 5 to 8 days for a double storey home. However, the total timeline from decision to site clearance is 6 to 10 weeks when you include the asbestos inspection, asbestos removal, service disconnections, and permit approvals. Service disconnections are the most common bottleneck, with electricity and gas abolishments taking 10 to 20 business days each. Plan for this lead time early to avoid delaying the start of your new build.