How Construction Loans Work When Building a New Home

Construction loans work differently to standard home loans. Here is how progress payments, drawdowns, and interest work when building.

Ashleigh Blake

share

If you are building a new home in Australia, you do not get a standard home loan. You get a construction loan. Understanding how does a construction loan work Australia wide is one of the most important steps before you sign a building contract, because the way money flows during a build is fundamentally different to buying an existing house.

With a regular mortgage, your lender releases the full loan amount at settlement. With a construction loan, funds are released in stages as the build progresses. You only pay interest on the amount drawn so far, not the total loan. That difference changes your cash flow, your repayment schedule, and the way you plan your finances across the build period.

Most first home buyers do not realise this until they are already in contract. This guide walks through every stage of the process, with real numbers, so you know exactly what to expect.

What is a construction loan and how is it different?

A construction loan is a home loan designed for building a new home. The lender does not release the full loan amount on day one. Instead, funds are drawn down in stages that align with the physical progress of your build.

With a standard home loan, you pay your deposit, the lender funds the balance at settlement, and you begin principal and interest repayments on the full amount immediately. A construction loan works differently in four key ways.

Progressive drawdowns. The loan is released in portions called drawdowns. Each drawdown is triggered when the builder completes a defined stage and submits a progress claim.

Interest only during construction. You only pay interest on the amount drawn down so far. Principal and interest repayments on the full loan begin once construction is complete.

Build period. Most lenders allow 12 to 24 months for construction. Extensions may be required if your build takes longer.

Builder approval. Your lender must approve your builder and your building contract before releasing any funds. The contract must be a fixed price domestic building contract with a registered builder.

At Senka, our fixed price contracts for new home builds are structured to align with lender requirements. Every stage is clearly defined, every inclusion is specified, and the total contract price is locked before construction begins. That clarity is not optional when your lender needs to approve the contract before releasing a single dollar.

How progress payments work at each build stage

In Victoria, progress payments follow a prescribed schedule under the Domestic Building Contracts Act 1995. These are the stages at which your builder claims payment and your lender releases funds.

The standard stages and their typical percentages of the total contract price are as follows.

Deposit: 5 percent, paid when you sign the building contract.

Base stage (slab): 10 percent, claimed when the concrete slab or footings are completed.

Frame stage: 15 percent, claimed when the structural frame is erected and the roof is on.

Lock up stage: 35 percent, claimed when the external walls, windows, doors, and roof covering are complete. The home is weather sealed.

Fixing stage: 25 percent, claimed when internal linings, cabinetry, wet area tiling, and internal fixtures are installed.

Completion: 10 percent, claimed when construction is finished and an occupancy permit has been issued.

Each time the builder completes a stage, they submit a progress claim to you. You forward that claim to your lender or broker. The lender may send a valuer or inspector to confirm the work, then releases the drawdown amount to the builder.

The process from claim to payment typically takes five to ten business days. This is why understanding the stages of building a home matters before you start. The payment schedule is prescribed by legislation to protect both homeowners and builders.

When you start paying interest

This is where the construction loan explained in practical terms makes the biggest difference to your budget.

You only pay interest on the cumulative amount drawn down. Your repayments start small and gradually increase as more money is released to the builder.

Here is a worked example based on a $450,000 building contract with a 4.5 percent variable interest rate. This assumes the 5 percent deposit ($22,500) was paid from your own funds at contract signing, so the loan drawdowns cover the remaining stages.

After base stage (slab) at 10 percent Amount drawn: $45,000 Monthly interest: approximately $169

After frame stage at 15 percent Cumulative drawn: $112,500 ($45,000 plus $67,500) Monthly interest: approximately $422

After lock up stage at 35 percent Cumulative drawn: $270,000 ($112,500 plus $157,500) Monthly interest: approximately $1,013

After fixing stage at 25 percent Cumulative drawn: $382,500 ($270,000 plus $112,500) Monthly interest: approximately $1,434

After completion at 10 percent Full loan amount drawn: $427,500 ($382,500 plus $45,000) Monthly interest: approximately $1,603

At this point, the construction loan converts to a standard home loan and you begin making principal and interest repayments on the full amount.

The total interest paid during an eight month build using these figures would be approximately $5,800. Compare that to paying interest on the full $427,500 from day one, which would cost approximately $12,825 over the same period. The progressive drawdown structure saves you roughly $7,000 during construction alone.

These numbers are indicative and will vary based on your rate, timeline, and drawdown spacing. But the principle is consistent. You pay interest on what has been used, not what has been approved.

Facade of a home built by Senka Homes

How drawdowns are structured

A construction loan drawdown is the mechanism by which your lender releases funds at each build stage. Understanding how construction loan drawdowns work helps you avoid payment delays that could affect your build timeline.

Here is how a typical drawdown works.

1. Your builder completes a defined stage of construction. 2. The builder issues a progress claim to you for the corresponding percentage of the contract price. 3. You review the claim against the work completed and sign off. 4. You submit the claim to your lender or broker with any required documentation. 5. The lender arranges a valuation or inspection to confirm the stage is complete. 6. The lender releases the drawdown amount directly to the builder.

Processing typically takes five to seven business days from receipt of a valid claim. There are a few things that can delay a drawdown.

Incomplete documentation. If the progress claim is missing information or does not match the contract stages, the lender will request clarification.

Valuation discrepancies. If the valuer assesses the completed work as less than the claimed stage, the lender may release a reduced amount.

Variations. If you have approved variations that change the total contract price, these need to be documented and approved by the lender before subsequent drawdowns can be processed.

At Senka, our progress claims are formatted to meet lender requirements. Each claim includes clear stage descriptions, corresponding percentages, and supporting documentation. This reduces friction and speeds up approvals.

What happens when the build is complete

When your builder issues the final progress claim and an occupancy permit has been issued, two things happen with your construction loan.

First, the final drawdown is released. Once paid, the full loan amount is drawn down.

Second, your construction loan converts to a standard home loan. This conversion is usually automatic, but the terms depend on what you negotiated at the outset. Some lenders lock in terms at application. Others reassess the interest rate at conversion.

Once converted, you move from interest only repayments to principal and interest repayments on the full loan balance. Using the earlier example of a $427,500 loan at 4.5 percent over 30 years, your monthly repayments would be approximately $2,167. That is a step up from interest only payments during construction, so plan your household budget around this transition.

If your fixed price contract included all inclusions as standard, there should be no surprise costs at handover. This is one reason why setting a realistic building budget before you start matters as much as choosing the right loan.

Fixed vs variable rates on construction loans

Most construction loans in Australia are variable rate during the construction period. The interest rate can move up or down while your home is being built. However, you have options.

Variable during construction, then fix at completion. The most common structure. You accept a variable rate during the build (typically 6 to 12 months) and lock in a fixed rate once the loan converts. The variable period is short, and the interest amounts are smaller due to progressive drawdowns.

Fixed rate from the start. Some lenders offer fixed rate construction loans, but they are less common. You are locked into that rate for the entire period, which may or may not work in your favour depending on rate movements.

Split loan. Part fixed, part variable once construction is complete. Partial protection against rate rises with some flexibility.

For most builders, the variable during construction approach works well because the interest amounts are relatively small. The decision becomes more significant once the full loan is drawn and principal and interest repayments begin.

A good mortgage broker will model these scenarios based on your specific loan amount and build timeline. If you are using a house and land package, the timeline is often more predictable, which makes the rate decision easier.

Open plan living area in a home built by Senka Homes

Tips for choosing a lender for a construction loan

Not all lenders handle construction loans well. Some have dedicated construction teams. Others treat it as an afterthought, and the processing delays reflect that. Here is what to look for.

Drawdown processing time. A lender that takes 14 days to process a drawdown can cause payment delays that affect your build schedule. Target lenders that consistently process within five to seven business days.

Builder panel requirements. Some lenders require your builder to be on their approved panel. Others accept any registered builder with valid domestic building insurance. If your preferred builder is not on a panel, that lender may not be the right choice.

Rate competitiveness. Construction loan rates are not always the same as standard home loan rates from the same lender. Compare the construction period rate and the rate that applies once the loan converts.

Flexibility on variations. Builds sometimes require approved variations that change the contract price. Some lenders handle this smoothly. Others treat every variation as a new application.

Broker recommendation. Ask your mortgage broker specifically which lenders they recommend for construction loans and why. Experienced brokers know which lenders perform well in practice, not just on paper.

If you are a first home buyer using the 5 percent deposit scheme, your lender must be a Housing Australia participating lender. Not all participating lenders are equally good at construction lending, so the broker’s guidance here matters.

How construction loans work with house and land packages

A house and land package involves two separate contracts. A contract of sale for the land and a building contract for the home. Your construction loan covers both, but the money flows differently for each part.

The land settlement. When the land settles, the lender releases the full land purchase price to the vendor. From this point, you are paying interest on the full land amount.

The construction drawdowns. Once land has settled and your builder has permits, construction begins. The building contract portion is drawn down in stages following the progress payment schedule described earlier.

This means during construction you are paying interest on the full land value plus whatever has been drawn down on the building side. Using an example of $350,000 land and the $450,000 build contract from earlier at 4.5 percent, here is what that looks like.

Stage Cumulative drawn Monthly interest
Land settlement (before construction) $350,000 $1,313
After base stage $395,000 $1,481
After frame stage $462,500 $1,734
After lock up stage $620,000 $2,325
After fixing stage $732,500 $2,747
After completion $777,500 $2,916

The total interest during an eight month build on this scenario would be approximately $19,200. That is a real cost that needs to sit in your budget alongside the build itself.

The gap between land settlement and construction commencement matters. If your land settles but construction does not start for three months due to permit delays, you are paying interest on the full land amount with nothing being built. Choosing a builder who manages the permit process efficiently is worth more than a marginal saving on the contract price.

Frequently asked questions

Do you pay a mortgage while your house is being built?

Yes, but not a full mortgage. During construction, you pay interest only on the amount drawn down so far. This starts small and increases at each build stage. Full principal and interest repayments begin once construction is complete and the loan converts to a standard home loan.

What are the stages of a construction loan?

A construction loan in Victoria follows the progress payment stages set by the Domestic Building Contracts Act. These are deposit (5 percent), base or slab (10 percent), frame (15 percent), lock up (35 percent), fixing (25 percent), and completion (10 percent). Your lender releases funds at each stage after verifying the work is complete.

How does a construction loan drawdown work?

A drawdown is triggered when your builder completes a construction stage and submits a progress claim. You review and approve the claim, then forward it to your lender. The lender verifies the work through a valuation or inspection, then releases the funds directly to the builder. This typically takes five to ten business days.

Can I get a construction loan with a 5 percent deposit?

Yes. Under the First Home Guarantee scheme, eligible first home buyers can secure a construction loan with a 5 percent deposit and no Lenders Mortgage Insurance. The scheme requires a fixed price building contract with a registered builder. Since October 2025, there are no income caps or place limits. The property price cap for Melbourne and Geelong is $950,000 for the combined land and build value.

Entry and hallway in a home built by Senka Homes

Where to start

A construction loan is not complicated once you understand the structure. You pay interest progressively, each drawdown requires documentation and approval, and the loan converts once the build is finished.

The most common issues arise when the builder’s contract does not align with lender requirements, or when drawdown processing is slow. Choosing the right lender and the right builder eliminates most of those friction points before they start.

If you are planning a new home build in Melbourne, talk to us. We walk every client through the payment structure before contracts are signed, so there are no surprises once construction begins.

Fixed price contracts are available on Senka house and land packages and dual occupancy projects, subject to site findings, with turnkey completion available as an option. Custom builds and knockdown rebuilds are priced to the individual site and scope. Your building contract sets out exactly what is included for your project.

WRITTEN BY

Ashleigh Blake

READ NEXT

More on this topic

Double storey home built by Senka Homes, facade lit in the evening

Architectural Design Without Architect Cost: The Third Option Most People Miss

How to get architectural quality without paying architect fees. The third option between project builders and full custom architects, and how Senka delivers design led homes.
White rendered double storey home by Senka Homes at dusk

Hamptons Style Home in Australia: What It Is, What It Is Not, and Whether It Works in Melbourne

What defines a Hamptons style home, whether it works in Melbourne, and how to incorporate Hamptons elements without committing to a full theme.
BoxHill Crayo

Is Building a Home Worth It in 2026? The Honest Case for Building Now

With costs rising everywhere, is building still a smart move? Here is the honest case for building a new home in Melbourne right now.

NEWSLETTER

Don't miss the next one

One email per month. Articles like this, market data, and build cost trends.

1,200+ subscribers · Unsubscribe anytime